Hi everyone - I have a few questions I haven't been able either to confirm or find answers for:
1. For Type VII U-boats, how long on average did it take to: (a) load a torpedo from the dock onto the boat? (b) reload a torpedo from the internal storage? 2. For G 7e torpedoes, I understand they needed on-board maintenance about every five days: (a) on average, how long did it take to complete this maintenance per torpedo? (b) did this maintenance include pre-warming? (c) if not, on average how often did the G 7e have to be pre-warmed and how long did it take to do so? 3. For G 7a torpedoes, am I correct that they did not require regular on-board maintenance or pre-heating? Thank you in advance! ![]() |
![]() |
![]() |
![]() |
#2 | |
Swabbie
![]() Join Date: Jan 2013
Location: Cologne Area, Germany
Posts: 11
Downloads: 9
Uploads: 0
|
![]() Quote:
![]() 1a) with dock-side cranes and no interruptions: about 45 minutes per eel. underway (reloading from external reserves), with calm seas and the boat-specific crane: at least 1.5 hours per eel. 1b) a good crew could reload all four tubes within 20 - 25 minutes. so, about 5 minutes per torpedo. Günther Prien during his Scapa Flow engagement fired 2 salvos (3 torpedoes each time) from his bow tubes at 00:58 AM and 01:13 AM, respectively. hope that helps ![]()
__________________
![]() Last edited by DJS4000; 08-04-20 at 09:59 AM. |
|
![]() |
![]() |
![]() |
#3 |
Nub
![]() Join Date: Jun 2017
Posts: 3
Downloads: 151
Uploads: 0
|
![]()
@DJS400 - Thank you! That's very helpful.
![]() |
![]() |
![]() |
![]() |