Quote:
Originally Posted by Bane
Yes it does. In most cases the doo doo doesn't delay the end date of the contract though. The contractor signed the deal, any doo doo that happens because of the contractor between beginning to end is the contractor's problem. The job ends on the date specified in the contract, doo doo or not.
|
well...not really.. if im building a building and dont finish up by the day i say i will i still have to finish it. i just dont get to charge the client for anything anymore.